Solution Services – Case Studies

Wapiti & South Wapiti Gas Processing Facility

Start Date: September 14, 2020
Completion Date: September 24, 2020

Timeline

CNRL Wapiti Plant start date was September 14th, estimated to take 8 days. Work was completed on the 20th, 1 day ahead of schedule. This project consisted of day and night shifts.

CNRL South Wapiti project start date was September 14th, estimated to take 14 days. Work was completed on the 24th, 3 days ahead of schedule.

Manpower

CNRL Wapiti saw a peak of 167 individuals under the management of Solution Services, with the total man hours worked coming in at 9,831.

CNRL South Wapiti had a peak of 84 individuals on site. The total man hours worked for on this project was 6,234.

Equipment Requirements

The list below shows the equipment that was required for the project. With these tools, we were able to make a collaborative effect in executing this project.

  • High Pressure Jetting Equipment (15K/20K/40K)
  • Zero Entry Cleaning Tools
  • Hot Oiler
  • Combo/ Vac Units
  • 45 Tonne Crane
  • Body Job Water Trucks
  • Pressure Trucks
  • 1 Tonne Tool Trucks
  • Hydraulic Torqueing Tools
  • Spyder Crane