2021 Project Highlights – Arc Resources
Description This 2021 Turnaround season has been the most successful season for Solution Services to date. A broad spectrum of clients and projects has allowed
KARR Creek Condensate Processing Facility
Start Date: September 8, 2020Completion Date: September 29, 2020 Zero Recorded Injuries 65,000 Manhours worked COVID Mitigation of 400+ workers – 6 Evacuations of perspective
Wapiti & South Wapiti Gas Processing Facility
Start Date: September 14, 2020 Completion Date: September 24, 2020 Timeline CNRL Wapiti Plant start date was September 14th, estimated to take 8 days. Work
CNRL Gold Creek
Project Scope CNRL Gold Creek was the final large scale turnaround of the 2019 season for Solution Services. A full 21 day station outage of