CNRL Gold Creek

Project Scope

CNRL Gold Creek was the final large scale turnaround of the 2019 season for Solution Services. A full 21 day station outage of a full sour C5+ process facility. This included inlet, stabilization, amine, process and compression. With a capital project cost of over 25 million dollars, Solution Services was responsible for the entire project planning and execution management scope. This included budget and schedule creation, updated facility LOTO procedure, as well as third party vetting. Solution Services provided manpower and equipment that included Maintenance Crews, Combo Vac’s, 15K & 40k Jetting and Blasting equipment as well as all supervision.

Project Stats

  • Responsible for managing a peak of 276 onsite workers
  • 100 + Solution Services employees
  • Successfully completed 48 hours ahead of schedule
  • 45,000 Total Labour Hours
  • 239 Safety Observations
  • 372 FLHA’s 

Zero Recorded Incidents

Our proudest statistic is that every single person who worked on this project went home safe to their families. 

Title