KARR Creek Condensate Processing Facility

Start Date: September 8, 2020
Completion Date: September 29, 2020

Zero Recorded Injuries

  • 65,000 Manhours worked
  • COVID Mitigation of 400+ workers – 6 Evacuations of perspective cases. 0 Positive tests.
  • Separate contractors involving 31 separate Management of Change projects communicated and executed ahead of schedule by all metrics

Timeline

Karr Plant start date was September 8th, estimated to take 26 days. Work was completed on the 29th, 4 days ahead of schedule. This project consisted of day and night shifts.

Manpower

KARR saw a peak of 365 individuals under the management of Solution Services, with the total man hours worked coming in at 64,827.

Equipment Requirements

The list below shows the equipment that was required for the project. With these tools, we were able to make a collaborative effect in executing this project.

  • Zero Entry Cleaning Tools
  • 40k High Pressure Lancing
  • 20K High Pressure Blasting
  • 2 Stage Caustic flush’s
  • 6 – <200Ton Cranes
  • 2- <150 HP Boilers
  • 2 – Hot Oiler’s
  • 14 – Combo/ Vac Units
  • 3 – 45 Tonne Crane
  • 2 – Body Job Water Trucks
  • 28 – 1 Ton Tool Trucks
  • 8 – Hydraulic Torqueing Tools
  • 2 – Spyder Crane
  • 4 – <80ft Ariel Work Platforms
  • 6 – >80ft Ariel Work Platforms

Title